Construction Photo Update 2-25-14
We
are really seeing the spaces coming together!
This week and next will be AMAZING!!!
The painters have been in and we have color. Plumbing is being connected. Ceiling grids are currently being installed
today, with tiles later this week.
Electrical outlets being installed & connected now.
Flooring to be coming later this week.
Cabinetry at the end of the week.
Furniture next week.
Th ey are working to enclose
the vestibule closest to the inside of the building so we will have access from
the inside hallways into the NEW office area.
March 7 is our anticipated date of receiving occupancy so we may begin
moving into the Office Space over the weekend, and be ready for school on
Monday, March 10. At that time, Phase 2
will begin which will include the repurposing of the old administration suite
into 2 new classrooms and finishing up the front entryway. Anticipated completion will be mid-April.