Tuesday, February 25, 2014

Construction Photo Update 2-25-14

We are really seeing the spaces coming together!  This week and next will be AMAZING!!!  The painters have been in and we have color.  Plumbing is being connected.  Ceiling grids are currently being installed today, with tiles later this week.  Electrical outlets being installed & connected now.  Flooring to be coming later this week.  Cabinetry at the end of the week.  Furniture next week.





They are working to enclose the vestibule closest to the inside of the building so we will have access from the inside hallways into the NEW office area.  March 7 is our anticipated date of receiving occupancy so we may begin moving into the Office Space over the weekend, and be ready for school on Monday, March 10.  At that time, Phase 2 will begin which will include the repurposing of the old administration suite into 2 new classrooms and finishing up the front entryway.  Anticipated completion will be mid-April.