One of the big jobs is to get our secondary vestibule built. Work started in building the door frames and wall, but will not be finished by March 7, so our "possession" has been delayed to March 14 now. Students will come back after Spring Break to see the New Office digs!
Most of the Carpet has been installed.
Ceiling Tile has been installed
Important Plumbing!
Reception Furniture being assembled.
Tar being placed on the roof. Yeah! Positive steps to getting our inner vestibules dry. The outer vestibule will continue to remain "Under Construction", while the inner or secondary vestibule will be completed so the office may be accessed from the inside of the building. We have a number of inspections set up for next week, as we approach the possibility of taking possession March 14. Fingers Crossed! And NO MORE SNOW! Please.....