Construction Updates - April 13

The shaping of the walls in our new front entryway
 


Paint and accent colors coming this week in the entryway!


 Inner Vestibule


New Early Childhood Class Room
 New Kindergarten Classroom


Sidewalk & Driveway Additions - to meet Slope Compliance Regulations, the Sidewalk and Driveway needed to be built up .  It was raised a little over a footThanks for everyone's understanding and patience while this occurred!


 

We may be close to seeing the light at the end of the tunnel, with the completion of Phase 2 of Construction - end of April is what they are currently telling me!   
Phase 3 will then begin this summer which will be the demolition of our current computer lab.  It will be relocated in the current 2nd grade pod, with the current computer lab becoming our Conference Room.
In addition, this summer we will have "lockers" installed in all of our pods and a new HVAC system replacing the 23 old heating and air conditioning unit.