Saturday, March 1, 2014

Construction Progress - Week of February 25th

Construction Progress - Week of February 25-29

Working to still get our "inside" vestibule closed in (roof, walls, & windows) for access to the office from the inside.  This will hopefully be completed this week so we may open the office up on Monday, March 10.
Concrete for the front entryway, which will continue to remain closed until Phase 2 is finished (estimated time frame of mid-April).

Floor Tile, lights, and cabinets installed in Teacher Lounge.

And for the Teacher Workroom.

Nurse's Office.